Within how many calendar days must the permit holder implement corrections after receiving an inspection report?

  1. 15 days

  2. 30 days

  3. 45 days

  4. 60 days

The correct answer is: 30 days

The requirement for the permit holder to implement corrections after receiving an inspection report is established to ensure that any identified issues are addressed promptly, thereby maintaining safety standards and regulatory compliance. In California, the regulation stipulates that the permit holder has a 30-day window to correct the violations noted in the inspection report. This timeframe is designed to balance the need for timely remediation with the practical considerations of sourcing materials and scheduling repairs. Completing corrections within this period helps to minimize risks associated with non-compliance, while also giving permit holders adequate time to address any findings thoroughly.